Hospitality · Montreal, QC

Radisson Hotel Montreal

LED mirrors and medicine cabinets delivered 3 days ahead of schedule — saving $42,000 in avoided delay penalties.

DESIGNED IN CANADA
EXTENDED WARRANTY
TRUSTED ACROSS NORTH AMERICA
$42K
Penalties Avoided
3 Days
Ahead of Schedule
0.9%
Breakage Rate
0
Defects
HospitalityMontreal, QC8 weeks

The Radisson Montreal Airport needed a full-floor mirror and cabinet renovation across multiple floors while maintaining partial hotel operations. The airport location added security complexity, the brand required specific LED color temperatures, and the contractor faced $14,000/day penalties for schedule overruns. We delivered the entire order 3 days ahead of the contractual deadline.

Financial Impact

$42,000

Avoided delay penalties — delivered 3 days early vs. contractual deadline

$18,500

Vendor consolidation — single supplier for mirrors + cabinets eliminated coordination overhead

15%

Volume pricing on full-order commitment vs. quoted rates from 3 separate suppliers

The Challenge

01

Airport security protocols required advance scheduling for every delivery vehicle — no same-day adjustments possible

02

Radisson brand standards mandated specific 4000K LED color temperature and exact mounting heights (±2mm tolerance)

03

Renovation had to proceed floor-by-floor with occupied rooms above and below — zero noise/dust tolerance during guest hours

04

General contractor faced $14,000/day liquidated damages for schedule overruns past December 15th deadline

05

Existing electrical infrastructure varied by floor — original 1980s wiring vs. 2010 renovation wings

Our Solution

Pre-construction site survey mapped every room's electrical configuration — eliminated change orders during install

Phased manufacturing matched floor-by-floor schedule: Floors 3-5 (Week 2), Floors 6-8 (Week 4), Floors 9-11 (Week 6)

Airport security pre-clearance arranged for all delivery personnel — zero access delays across 8 weeks

Custom LED drivers configured to 4000K ±50K with dimming range meeting Radisson's brand compliance documentation

Dedicated project manager on-site 3 days/week coordinating with GC, electricians, and hotel operations

Our Work

From Montréal to the world.

What Our Partners Say

We had $14,000/day on the line if mirrors weren't ready. Hilo delivered 3 days early. That's not just on-time — that's $42,000 we didn't lose. They're now our go-to for every Canadian property.

VP Renovations

Radisson Hotel Group — Canada

Radisson Hotel Montreal

Montreal, QC

READY TO GET STARTED?

Ready to See Similar Results?

Get your project quote with verified timelines and pricing.

DESIGNED IN CANADA
EXTENDED WARRANTY
TRUSTED ACROSS NORTH AMERICA

No commitment. No obligation. Just fast, accurate pricing.